The FLEXMETER project is organized in 6 technical WPs and 2 management WPs as depicted in the Figure 4. Among the technical WPs, WP1 will provide specifications about the technologies to be developed in WP2, WP3 and WP4. There will be a dependency for this reason between the completion of WP1 and the beginning of activities in WP2/3/4.
WP5 will explore market impacts and business models. As such it will start right after specifications and run in parallel with respect to WP2/3/4.
Finally, WP6 where the demonstration activities are concentrated, will start after the technologies are at an advanced stage of completion.WP7 and WP8 about exploitation, dissemination and management will run in parallel for the whole duration of the project.