The FLEXMETER project is organized in 6 technical WPs and 2 management WPs as depicted in the Figure 4. Among the technical WPs, WP1 will provide specifications about the technologies to be developed in WP2, WP3 and WP4. There will be a dependency for this reason between the completion of WP1 and the beginning of activities in WP2/3/4.

WP5 will explore market impacts and business models. As such it will start right after specifications and run in parallel with respect to WP2/3/4.

Finally, WP6 where the demonstration activities are concentrated, will start after the technologies are at an advanced stage of completion.WP7 and WP8 about exploitation, dissemination and management will run in parallel for the whole duration of the project.

 

Work packages description

WP1 – System specification

WP2 – Prosumer-side smart metering architecture and development

WP3 – Smart-grid integration

WP4 – Smart meter services and data management

WP5 – Business models

WP6 – Demonstration and evaluation

WP7 – Dissemination and Exploitation

WP8 – Management